City Edge Alliance
Mangaonua Gully:
The project involved construction of a new stream alignment under live flows and Regional Council Consents and Monitoring. Installation of Rip Rap Lining, Overpumping/Dewatering and Bulk Earthworks associated with Cut to Filling the old steam route.
Resolution Dr:
The project involves construction of 2km of local road from sub-grade to top of SIL including swale drain formation and lining. 200,000m3 of SIL import and placement.
4km of Lined Swale Drain formation inclusive of management of live flows from clean water farm drains. Swale Drains 15m in width and up to 2.5m in depth.